NASA Moon Base contracts: awards, flights and schedules

The "$10 billion" Moon Base contract NASA announced on November 7, 2026 is a ceiling shared by 8 companies, not money handed out. Across 7 matched announcement rows for CLPS and Moon Base-related procurement in 2026, NASA announced $1,397.8 million. USAspending recorded $472.2 million in lifetime net obligations on the same 9 task orders when checked on November 9, 2026. 3 rows use a June match we worked out from the evidence, and these totals cover only the matched subset. NASA and JPL sources list all 6 missions in our schedule table as future missions when checked on November 9, 2026.

Updated

$10B

CLPS 2 ceiling, shared by 8 companies

$1.4B

Announced value, 7 matched rows

$472.2M

Recorded net obligations, same rows

0 of 6

Missions in our schedule table launched. Selected coverage, not the full program inventory.

The full Moon with its dark maria and bright cratered highlands
A computer visualization of the full Moon, built from elevation measurements by the Lunar Reconnaissance Orbiter. Visualization: NASA Goddard.

This page separates announced values, optional work, shared contract ceilings and recorded obligations. It also shows the lunar lander flights linked to the companies NASA selected, and every mission target we found, statement by statement.

Located CLPS and Moon Base procurement announcements

An obligation is a government commitment to spend money; an outlay is a payment. The figures here are lifetime net obligations recorded by USAspending.gov when checked on November 9, 2026, including any reductions to earlier obligations. They aren't payments, spending in 2026 only, or a measure of how far a project has got.

This is an inventory of the NASA announcements we located from January 1, 2026 to November 9, 2026, not every procurement action, grant or science selection. It includes the March 27 Nova-D CLPS award, whose announcement describes CLPS and Artemis without naming Moon Base. Launch orders for Earth-orbit missions under the same VADR contract are left out.

Located awards and contractor selections, checked November 9, 2026
AnnouncedProgrammeCompanyForAnnounced valueOptionObligated so farSource
March 27, 2026CLPS 1.0Intuitive MachinesFifth CLPS delivery, Nova-D, lunar South Pole, NASA landing target 2030$180.4 million-$46.8 millionNASA (opens in a new tab)
May 26, 2026LTVSAstrolabPhase 1 High Achievability Mission task order for first-phase LTV$219.0 million-$87.6 millionNASA (opens in a new tab)
May 26, 2026LTVSLunar OutpostPhase 1 High Achievability Mission task order for first-phase LTV$220.0 million-$121.0 millionNASA (opens in a new tab)
May 26, 2026CLPS 1.0Blue OriginTwo task orders to deliver Astrolab and Lunar Outpost LTVs to the lunar South Pole region$188.0 million$280.4 million$101.5 millionNASA (opens in a new tab)
May 26, 2026MoonFall / Moon BaseFirefly AerospaceBuild the spacecraft transporting JPL MoonFall drones from Earth orbit to the Moonnot disclosed-not matchedNASA (opens in a new tab)
June 30, 2026CLPS 1.0AstroboticCS-8 lunar surface science deliveries, targeting late 2028$297.9 million-$48.3 million *NASA (opens in a new tab)
June 30, 2026CLPS 1.0Firefly AerospaceCS-8 lunar surface science deliveries, targeting late 2028$144.2 million-$31.3 million *NASA (opens in a new tab)
June 30, 2026CLPS 1.0Intuitive MachinesCS-8 lunar surface science deliveries, targeting late 2028$148.3 million-$35.7 million *NASA (opens in a new tab)
July 24, 2026Moon Base / CAPSTONE 02Advanced SpaceTwo-spacecraft cislunar technology demonstrationnot disclosed-not matchedNASA (opens in a new tab)
September 30, 2026Moon Base communicationsModulate Space Corporation5G communications system with Wi-Fi 6, lab and lunar surface flight demonstrations$38.0 million-not matchedNASA (opens in a new tab)
November 7, 2026PROMISE / CLPSBlue OriginDeliver PROMISE rover to lunar South Pole with Blue Moon Mark 1$94.0 million$140.0 millionnot matchedNASA (opens in a new tab)
November 7, 2026VADRArrow Science and Technology, Blue Origin, Impulse SpaceSix launch and orbital transportation task orders supporting Moon Base cargo, CAPSTONE 02, MoonFall and cislunar demonstrations$1.3 billion-not matchedNASA (opens in a new tab)
November 7, 2026Moon Base lunar logisticsSpaceXSpecialized Delivery Mission task order: Cislunar Communications Deployment Demonstration on Starship in 2028not disclosed-not matchedNASA (opens in a new tab)
November 7, 2026NextSTEP-3 B / miniCASTHoneybee RoboticsminiCAST energy storagenot disclosed-not matchedNASA (opens in a new tab)
November 7, 2026NextSTEP-3 B / miniCASTRedwireminiCAST power generationnot disclosed-not matchedNASA (opens in a new tab)
November 7, 2026NextSTEP-3 B / miniCASTYank Technologies, Inc.miniCAST wireless power transfernot disclosed-not matchedNASA (opens in a new tab)

"Not disclosed" means NASA gave no value; "not matched" means we couldn't tie the announcement to a federal record with confidence, not that nothing has been obligated. Where NASA gives one figure for several orders, we don't split it. * June matches are worked out by us, not award numbers NASA published: we listed the orders under each company's CLPS parent contract and matched the company, the June 30 signing date, the number of deliveries and a combined value within $100,000 of NASA's figure. Every obligation figure was checked against the signed transactions behind it, including negative ones. The CSV below links each figure to its USAspending.gov record.

Ceilings aren't awards

A ceiling is the most NASA can spend through a contract over its life. Companies still have to win individual orders under it.

Contract ceilings in the November 7, 2026 announcement
ContractWho can win ordersCeilingWhat it means
CLPS 2 (new, 10 years)Blue Origin, Firefly Aerospace, Intuitive Machines, ispace-U.S., Lockheed Martin Space, Northrop Grumman Space Systems, SpaceX, Voyager Technologies$10 billionEligibility to compete for task orders. Not money awarded to any company.
CLPS (original contract)Existing CLPS companies$2.6 billion to $4.2 billionRaised by $1.6 billion, 61.5 percent. New orders until November 2028, deliveries can finish by November 2033.
VADR launch and transportAll VADR companies$5 billionMaximum across all VADR contracts. The Moon Base orders announced on November 7, 2026 are $1.3 billion combined, shared by Arrow Science and Technology, Blue Origin, Impulse Space.

Which companies have flown a lunar lander

2 of the 8 companies in the new contract, Firefly Aerospace and Intuitive Machines, have landed on the Moon with their own landers. 2 more, ispace-U.S. and Voyager Technologies, are linked to failed attempts by a parent company or a business they bought. For the other 4, Blue Origin, Lockheed Martin Space, Northrop Grumman Space Systems and SpaceX, our ledger has no lunar lander flight. Grades come from our Moon mission ledger and measure each mission against its own goals, so a lander that tipped over can still count as a success.

Lunar lander flights linked to the 8 CLPS 2 companies
CompanyMissionLaunchedOur gradeWhat happened
Blue OriginNone matched--No historical lunar lander-operator mission matched in our ledger. This doesn't assess launch, manufacturing, subsystem or other experience.
Firefly AerospaceBlue Ghost Mission 12025successOperator reports all mission objectives met after full lunar-day surface operations.
Intuitive MachinesIM-12024successDelivered instruments and returned surface data for the projected seven-day program despite tipped attitude.
Intuitive MachinesIM-22025partialTipped landing prevented drilling into regolith and mobile operations, but surface payload engineering tests returned data.
ispace-U.S.HAKUTO-R Mission 12022failureFlown by the Japanese parent company, ispace. Crash landing prevented the primary surface delivery and rover operations, despite completion of eight preparatory milestones.
ispace-U.S.HAKUTO-R Mission 22025failureFlown by the Japanese parent company, ispace. Crash landing prevented surface payload delivery and Tenacious deployment.
Lockheed Martin SpaceNone matched--No historical lunar lander-operator mission matched in our ledger. This doesn't assess launch, manufacturing, subsystem or other experience.
Northrop Grumman Space SystemsNone matched--No historical lunar lander-operator mission matched in our ledger. This doesn't assess launch, manufacturing, subsystem or other experience.
SpaceXNone matched--No historical lunar lander-operator mission matched in our ledger. This doesn't assess launch, manufacturing, subsystem or other experience.
Voyager TechnologiesPeregrine Mission One2024failureFlown by Astrobotic before Voyager bought it. Propellant leak prevented lunar landing and surface delivery; spacecraft reentered Earth atmosphere.

NASA mission targets, statement by statement

These are the target statements we located from May 26, 2026 to November 9, 2026, grouped by mission. Launch, arrival, landing and general mission timing are kept apart, and vague dates stay vague: we don't turn approximate targets into a number of months late. Years in brackets clarify relative wording. Current pages are what the page said when we read it, not evidence of when a target changed.

Mission targets in the sources we located
MissionSaid onEventTarget as statedSource
Moon Base IMay 26, 2026Launchno earlier than fall 2026NASA (opens in a new tab)
Moon Base IMay 26, 2026 remarks; May 27, 2026 publishedLaunchFall 2026, no earlier thanNASA (opens in a new tab)
Moon Base ISeptember 15, 2026Launchthe first part of 2027Aerospace America (NASA official quoted) (opens in a new tab)
Moon Base ICurrent page, read November 9, 2026Launch2027NASA (opens in a new tab)
Moon Base IIMay 26, 2026Launchlater this year [2026]NASA (opens in a new tab)
Moon Base IIMay 26, 2026 remarks; May 27, 2026 publishedLaunchbefore the end of 2026NASA (opens in a new tab)
Moon Base IIAugust 4, 2026Launchlate 2026NASA (opens in a new tab)
Moon Base IIAugust 14, 2026 recorded; September 11, 2026 publishedMission / delivery, not explicitly a launch dateperhaps next year [2027]NASA (opens in a new tab)
Moon Base IISeptember 15, 2026Launchno earlier than November [2026]Aerospace America (NASA official quoted) (opens in a new tab)
Moon Base IIOctober 13, 2026Launchlater this year [2026]NASA (opens in a new tab)
Moon Base IIOctober 20, 2026Launchlate 2026NASA (opens in a new tab)
Moon Base IICurrent page, read November 9, 2026LaunchLate 2026NASA (opens in a new tab)
Moon Base IIIMay 26, 2026Launchthis year [2026]NASA (opens in a new tab)
Moon Base IIIMay 26, 2026 remarks; May 27, 2026 publishedLaunchbefore the end of 2026NASA (opens in a new tab)
Moon Base IIISeptember 15, 2026Launchthe first part of 2027Aerospace America (NASA official quoted) (opens in a new tab)
Moon Base IIICurrent page, read November 9, 2026LaunchEarly 2027NASA (opens in a new tab)
MoonFallMay 26, 2026Launch2028NASA (opens in a new tab)
MoonFallOctober 21, 2026Landing2028NASA (opens in a new tab)
MoonFallCurrent page, read November 9, 2026Arrival2028NASA (opens in a new tab)
MoonFallCurrent page, read November 9, 2026Landingby 2028NASA (opens in a new tab)
PROMISENovember 7, 2026Launchlate 2028NASA (opens in a new tab)
PROMISECurrent page, read November 9, 2026Launchlate 2028NASA (opens in a new tab)
Cislunar communications demoNovember 7, 2026Launch2028NASA (opens in a new tab)

Moon Base I is Blue Origin's Blue Moon Mark 1 lander, Endurance. Moon Base II is Astrobotic's Griffin lander, now part of Voyager, carrying the FLIP rover. Moon Base III is Intuitive Machines' IM-3 lander, Trinity, bound for Reiner Gamma rather than the south pole. A NASA podcast recorded on August 14 gave a tentative 2027 for Moon Base II, while later NASA articles and its event page say late 2026; both are listed. NASA's older CLPS deliveries page still shows a 2025 date for Griffin, which we treat as out of date. This table covers selected missions, not the whole Moon Base program.

PROMISE, MoonFall and the SpaceX demonstration

PROMISE is a planned six-wheeled JPL rover with a drill designed to sample material from about 1 meter below the surface. (November 7 release (opens in a new tab)) NASA plans a late-2028 launch and an 18-month primary mission. (PROMISE mission page (opens in a new tab)) Its planned power source is an MMRTG, which makes electricity from the heat of radioactive decay; it isn't a reactor. (how NASA radioisotope power works (opens in a new tab)) NASA announced $94 million in base work for Blue Origin to deliver it, with a further $140 million option that depends on performance. (November 7 release (opens in a new tab)) MoonFall is planned to send four JPL-built propulsive drones aboard Firefly's Elytra spacecraft. (MoonFall mission page (opens in a new tab)) NASA's May announcement targeted MoonFall's launch for 2028. (May 26 release (opens in a new tab)) NASA also gave SpaceX a separate order to demonstrate deploying communications satellites from Starship into the space between Earth and the Moon in 2028, without disclosing its value. (November 7 release (opens in a new tab))

Cite this page

Space Osmosis. "NASA Moon Base contracts: awards, flights and schedules." https://spaceosmosis.com/missions/moon/nasa-moon-base-contracts/. Updated November 9, 2026. Accessed November 18, 2026 (the date this page was built; use the date you read it).

Reuse original charts, tables and figures, including commercially, with credit to Space Osmosis. An online source link is appreciated. Photos and third-party data keep their own licences. Reuse details.